The Rack Is the Easy Part
Racking comes apart and goes back up in days. Moves lose a week when the new building is not ready, parts are not labeled, the permit is not filed, or the plan was drawn for the old column grid.
Eight Weeks Out: Survey and Draw
- Survey what you have: make, style, upright heights and depths, beam lengths and capacities, deck sizes, quantities, and damage. Damaged uprights get replaced, not moved.
- Measure the new building: clear height, column grid, dock, sprinklers, floor. Draw a new layout around the new columns and truck aisles (layout guide).
- Decide what moves and what is new. If the new building wants taller uprights or a dense block, sell the old rack to our yard against new.
Six Weeks Out: Permits and Schedule
- File the permit at the new address once the layout is final. Review takes two to eight weeks and is the long pole.
- Book install crew, trucks and forklifts for the new site and the teardown crew for the old one. Confirm dock access and hours at both ends.
- Order replacement parts now: anchors (never reused), safety clips, column protectors, row spacers, any new uprights or beams, and load plaques for the new layout.
Two Weeks Out: Label and Stage
- Number every row and bay on the drawing and the steel, with paint pen or tags. Bundle beams, uprights and decks by row.
- Empty the rack in order: the last rows down are the first up at the new site. Product moves on the same schedule.
- Inspect while empty. Replace bent columns, torn footplates, cracked welds and damaged connectors.
Teardown
- Decks and accessories offWire decks stacked flat on pallets by size, clips and spacers in bins.
- Beams out, top downLevel by level from a lift, bundled by length and row.
- Rows unboltedRow spacers off, anchors cut flush or pulled, uprights laid flat and bundled by height.
- Floor made goodAnchor holes patched if the lease requires it.
- Loaded in reverse orderRows needed first at the new site load last.
A crew takes down 150 to 250 bays a day depending on height, with forklift and lift on site.
Re-Install
- Lines snapped from the approved drawing; column grid and aisles checked before the first upright stands.
- Uprights set, plumbed, shimmed and anchored with new wedge anchors to the engineer's spec.
- Beams at the drawing's levels (not the old ones), every clip locked.
- Decks, row spacers, column protectors, end-of-aisle guards, load plaques.
- Inspection against the drawing and the inspection checklist, then the fire marshal's visit.
Re-install runs 150 to 250 bays a day.
What Usually Gets Replaced
- Anchors, every time.
- Damaged uprights, usually 5% to 10% of a well-used rack.
- Safety clips (lost or bent).
- Load plaques (new layout, new numbers).
- Sometimes beams, if the new beam spacing calls for different lengths.
What It Costs and How Long
Moving existing rack costs 30% to 50% of new installed, before replacements. A 300-bay warehouse comes down in two days, moves in two to four trailer loads, and goes up in two to three days, with the permit approved before the crew arrives. We do both ends: installation and teardown.